ANALISIS PERENCANAAN PERAWATAN SPINDLE MOULDER DENGAN METODE RELIABILITY CENTERED MAINTENANCE (RCM) DI PT. ROMI VIOLETA
ANALISIS PERENCANAAN PERAWATAN SPINDLE MOULDER DENGAN METODE RELIABILITY CENTERED MAINTENANCE (RCM) DI PT. ROMI VIOLETA
Muhammad Ardian Firmansyah
Universitas Jember
Ahmad Syuhri
Universitas Jember
DOI: https://doi.org/10.19184/rotor.v15i1.29360
ABSTRACT
In a furniture company, there are several production machines that are used and in the process are interconnected. The production machines used often experience downtime or machine failure. One of which is the spindle moulder machine, it is a cutting machine used to cut wood with various profiles as needed. Damage to this machine can cause the production process to stop, so that downtime will increase and the production target that has been set will be reduced. To maintain the working condition of the machine so that it can last a long time and run optimally, the initial step is in the form of scheduling maintenance. RCM is a strategy to optimize the company's asset maintenance program so that it can operate effectively. This research method uses quantitative analysis conducted on the spindle moulder machine and qualitative analysis includes FMEA and RCM II Decision Worksheet which will be used as references to identify component failures and determine appropriate maintenance actions. The research results, the availability value for the spindle bearing component is 99.72%, the motor component is 99.78%, and the v belt component is 99.77%, so the average availability value is 99.76%. The value of downtime after preventive maintenance using the RCM method on the spindle moulder machine is 43.54 hours with a decrease in machine downtime of 30.96 hours (41.55%).
Keywords: RCM, FMEA, Availability.
REFERENCES
[1] Gaspersz, V. 1992. Analisis Sistem Terapan Berdasarkan Pendekatan Teknik Industri. Bandung: Tarsito.
[2] Moubray, J. 1997. Reliability Centered Maintenance II. 2nd ed. Woburn: Butterworth-Heinimann, Ltd.
[3] Syahrudin, S. 2013. Analisis Sistem Perawatan Mesin Menggunakan Metode Reliability Centered Maintenance (RCM) Sebagai Dasar Kebijakan Perawatan yang Optimal di PLTD “X”. JTT (Jurnal Teknologi Terpadu). 1(1).
[4] Taufik, T., & Septyani, S. 2016. Penentuan interval waktu perawatan komponen kritis pada mesin turbin di PT PLN (Persero) Sektor Pembangkit Ombilin. Jurnal Optimasi Sistem Industri. 14(2): 238-258.
[5] Ahmadi, N., & Hidayah, N. Y. 2017. Analisis pemeliharaan mesin blowmould dengan metode RCM di PT. CCAI. Jurnal Optimasi Sistem Industri. 16(2): 167-176.
[6] Kirana, U. T., Alhilman, J., & Sutrisno, S. (2016). Perencanaan Kebijakan Perawatan Mesin Corazza FF100 Pada Line 3 PT XYZ Dengan Metode Reliability Centered Maintenance (RCM) II. JRSI (Jurnal Rekayasa Sistem dan Industri). 3(01): 47-53.
[7] Kurniawan, K., & Rumita, R. (2014). Perencanaan Sistem Perawatan Mesin Urbannyte Dengan Menggunakan Metode Reliability Centered Maintenance II (RCM II)(Studi Kasus di departmen produksi PT. Masscom Graphy, Semarang). Industrial Engineering Online Journal. 3(4).
[8] Ariani, D. W. 2005. Pengendalian Kualitas Statistik (Pendekatan Kuantitatif Dalam Manajemen Kualitas).Yogyakarta: Andi.
[9] O Soesetyo, I., & Bendatu, L. Y. (2014). Penjadwalan Predictive Maintenance dan Biaya Perawatan Mesin Pellet di PT Charoen Pokphand Indonesia-Sepanjang. Jurnal Titra. 2(2): 147-154.
[10] Heizer, J. dan Render B. 2010. Manajemen Operasi. Edisi 7. Jakarta: Salemba Empat.
[11] Winarno, H., dan S. Y. Negara. 2014. Analisis Productive Maintenance di PT Sankyu Indonesia Internasional. Jurnal Intech Teknik Industri. 4(2): 24-32.
[12] Gupta, G., Mishra, R. P., & Singhvi, P. 2016. An Application Of Reliability Centered Maintenance Using RPN Mean And Range On Conventional Lathe Machine. International Journal of Reliability, Quality and Safety Engineering. 23(06): 1640010.
[13] Ridhawati, A. 2015. Analisis Keandalan Mesin High Frequency Welding di Plant Kt 24 PT. Bakrie Pipe Industries. Skripsi. Jakarta: Fakultas Teknik Industri Universitas Bakrie.
[14] Bangun, I. H., Rahman, A., & Darmawan, Z. (2014). Perencanaan Pemeliharaan Mesin Produksi Dengan Menggunakan Metode Reliability Centered Maintenance (RCM) II Pada Mesin Blowing OM (Studi Kasus: PT. Industri Sandang Nusantara Unit Patal Lawang). Jurnal Rekayasa dan Manajemen Sistem Industri. 2(5): 997-1008
[15] Mutiara, S. D., Rahman, A., & Hamdala, I. (2014). Perencanaan Preventive Maintenance Komponen Cane Cutter I dengan Pendekatan Age Replacement (Studi Kasus di PG. Kebon Agung Malang). Jurnal Rekayasa dan Manajemen Sistem Industri. 2(2): 396-405
[16] Suryana, M. T. A., Novareza, O., & Darmawan, Z. (2015). Perencanaan Perawatan Pulverizer dengan Menggunakan Metode Reliability Centered Maintenance (RCM) II (Studi Kasus di PT. YTL PAITON). Jurnal Rekayasa dan Manajemen Sistem Industri. 3(8): 1760-1771.
Published
30-06-2022
Issue
Vol. 15 No. 1: 2022: ROTOR: Jurnal Ilmiah Teknik Mesin
Pages
17-25
License
Copyright (c) 2022 ROTOR:Jurnal Ilmiah Teknik Mesin
How to Cite
Firmansyah, M.A. and Syuhri, A., 2022. Analisis Perencanaan Perawatan Spindle Moulder Dengan Metode Reliability Centered Maintenance (RCM) Di PT. Romi Violeta. ROTOR, 15(1), pp.17-25. https://doi.org/10.19184/rotor.v15i1.29360
Download Citation
RIS
BibTeX